Back to Projects

Ballinderry Footbridge

  • Civil Engineering
  • ClientDRD Roads Service
  • Value£160,000
  • Duration12 weeks
  • D&B Partner DRD Road Service
Ballinderry Footbridge

Design & build supply and installation of a single span pedestrian footbridge, including reinforced concrete bearing seats, reinforced concrete piled supports, footway construction, and earthworks.

Feature of ProjectConcept Design

Our supply chain partner, M Hassan & Sons, developed the Transport NI concept design to provide a 44m span bow warren design steel footbridge, with rectangular hollow section members and circular hollow section top chord. The footbridge was manufactured off-site in three sections, and welded together on-site before being lifted into position. Handrails were fitted after the bridge was positioned, and an anti-slip surfacing was applied before opening the bridge to the public.

Concept Design