Project

Fenton Dock Berths 7 and 9 Reconstruction, Runcorn

Icon for Civil Engineering

Civil Engineering

Icon for Ports & Harbours

Ports & Harbours

Icon for Northern England

Northern England

Featured Image for Fenton Dock Berths 7 and 9, Runcorn

Client

Peel Ports Ltd

Value

£3,300,000

Duration

52 weeks

D&B Partner

RPS

Fenton Dock was constructed between 1873 and 1875 as an expansion of Runcorn Docks.

The intention was to have a direct connection to the River Mersey for ocean-going ships. As well as a connection to the Runcorn & Weston Canal for smaller inland waterways traffic.

Consequently it was connected to the Manchester Ship Canal. Then disconnected from the Runcorn and Weston Canal when the canal was later abandoned and infilled.

The dock is used for dry bulk cargoes unloaded using tracked excavators, portable vacuum unloaders or directly into a fixed pipe connection for self-discharging vessels. There are two bulk warehouses directly behind the quay wall.

The quay wall which was not operational following a collapse of the existing dock wall.

Our works included the demolition of where the structure was damaged but still in place. Then the reconstruction of 110m of quay wall on Berths 7 and 9 within Runcorn Docks.

Additionally, the project also included the provision of two working berths for use by general and bulk cargo vessels, with a draught of 7m and up to 7000t.

The remaining berths within the dock, including berths 6 and 8 directly opposite, and the landside areas remained live at all times. We worked collaboratively with the port’s operations team to deliver the project whilst ensuring minimal disruption.

The docks are impounded with water levels controlled by a series of locks and sluice gates. However, there was still a variation in levels daily depending on the port’s operational requirements and the vessel using the canal. We planned our works around Peel Ports’ operational requirements with continual communication with key stakeholders. This was particularly important during the construction of the cope beam sections as unexpected raising of water levels could have caused damage to the works.

Newsletter Sign Up

Newsletter