Projects

Works to begin at King Edward VIII Pier

Date Posted 13.09.23

We are delighted to have been awarded a major engineering project designed to protect critical marine infrastructure at King Edward VIII Pier in Douglas Harbour.

The alterations to the pier include the installation of two new large steel piles around the end of the pier. As well as the installation of three new 100-ton mooring bollards close to the linkspan. Works also include modifying the fenders which prevent a vessel from colliding with the harbour wall.

The improvements are necessary due to the arrival of the Isle of Man Steam Packet Company’s new vessel, Manxman.

They also form part of the wider Harbour Strategy approved by Tynwald in 2018. Which included an upgrade to the pier to accommodate a larger vessel as a replacement for the Ben-my-Chree.

While Manxman has been designed specifically for Douglas Harbour, and can be berthed and manoeuvred exactly as planned. It is 8m longer and 3m wider than the Ben-my-Chree and weighs almost twice as much; 24,161 tonnes compared to 12,504 tonnes.

Fenders and mooring bollards will therefore be replaced and strengthened to reduce the risk of damage to both the pier and new vessel during Force 10 winds.

Works also include repairs to the pier wall, and the placement of rock bags to provide protection for the pier from underwater scour caused by the fast moving water around the vessel’s propellers.

The arrival of the Manxman and its entry into service marks an exciting time in our modern maritime history. Existing facilities are able to accommodate the vessel under benign conditions, but must be updated in order to protect Manxman and its berth from very high winds. The boat’s greater size compared to the Ben-my-Chree has been noted by many since its arrival, but its substantial weight difference is a critical factor in making these changes as we head into winter. Protecting and improving our national infrastructure is key to delivering the aims of Our Island Plan and this once-in-a-generation project will serve our community well for many years to come.

Chief Minister Alfred Cannan MHK

Infrastructure Minister at UK Government

McLaughlin & Harvey is delighted to have been awarded this critical marine infrastructure project for King Edward VIII Pier. We bring with us extensive experience in the marine sector and look forward to engaging with our local supply chain and creating jobs locally. Over the next couple of weeks, we will undertake the temporary diversion of the existing passenger walkway to facilitate the project along with mobilisation of plant and materials to construct the new berthing and fender dolphins.

Gareth Brennan

Project Director at McLaughlin & Harvey

Newsletter Sign Up

Newsletter