Back to Projects

Moira Railway Station Footbridge

  • Civil Engineering
  • ClientTranslink
  • Value£480,000
  • Duration23 weeks
  • Employers Representative Atkins
Moira Railway Station Footbridge

Construction of a new single span steel footbridge with bespoke cladding and access steps to replace the pedestrian level crossing at Moira Station.

Works included a platform extension to accommodate the new bridge which was installed in a single overnight possession.

McLaughlin & Harvey were responsible for design elements, fabrication, installation and commissioning of a new footbridge at Moira Station, spanning twin track railway on the main Belfast to Dublin railway line.

Mini-piles for the bridge foundations were installed on the railway platform and the platforms were also extended. Associated works included installation of ducts and cabling, fencing, gates and surfacing works.

Would you like to discuss a project?

Contact