Back to Projects

Cloghan Point Soil Nailing, Larne

  • Civil Engineering
  • ClientTranslink
  • Value£110,000
  • Duration6 weeks
  • Engineer URS
Cloghan Point Soil Nailing, Larne

Stabilisation of a steep railway cutting on the Belfast to Larne railway line using soil nailing installed via roped access techniques and rail mounted plant.

Feature of ProjectEmbankment

This project followed previous unsuccessful attempts by others to pin the embankment and entailed 147 soil nails drilled to a depth of 10m and installation of geomat covering an area of approximately 500sqm.

We maximised opportunities to conduct non-trackside works with access and working areas established from adjacent land avoiding impact on railway operations and optimising site & track safety.

Embankment

Would you like to discuss a project?

Contact