Back to Projects

Ballymena to Coleraine Track Life Extension

  • Civil Engineering
  • ClientTranslink
  • Value£9,000,000
  • Duration60 weeks
  • Employers Representative Doran Consulting
Ballymena to Coleraine Track Life Extension

Upgrade of 26 track miles of railway line between Ballymena and Coleraine to increase the life of the existing track and increase line speed.

Works included the construction of a temporary maintenance pit and shed, welding of 26 miles of track, delivery of rail string to site, new formation with associated drainage for 6 miles, replacement of 3 under bridges, waterproofing of 19 under bridges, ballast retention and embankment regrading.

Platform works were also included as part of the project due to concern over the stability of the existing platforms.

Would you like to discuss a project?

Contact