Back to Projects

Translink Track Safety Improvements

  • Civil Engineering
  • ClientTranslink
  • Value£1,300,000
  • Duration64 weeks
  • Employers Representative Arup
Translink Track Safety Improvements

Part of the overall scheme to extend the life of the Coleraine to Derry railway.

A total length of 18.5 miles was re-railed between Castlerock and Eglinton, including improvements to culverts.

“To do it in the time scales for such a long distance, 18 miles in 2 months…McLaughlin & Harvey stepped up very well, they got themselves very well organised…they knew what they were doing. The process was well controlled and done very efficiently.”
Andrew McGivern, NIR District Engineer