Specialist laboratory completed

24.11.15

Seapark Specialist Laboratory was completed 16 November on-time and snag free.

The design and build project included 4-storey 41,441sqft laboratory accommodation and offices.

Works also included 240 car park spaces. The building comprises in-situ concrete and flat slabs, brickwork, curtain wailing and rainscreen cladding.

The 78 week contract was undertaken in 2 phases; phase 1 car park was carried out in 12 weeks, and phase 2 main building was completed in 66 weeks.