McLaughlin & Harvey are pleased to announce completion of the Stevenson College North Campus development.

Managed by our Contract Manager Phonsie Taggart and Site Manager Francois Viljoen, the project involved the extension of the existing building, construction of a new atrium space and link corridor, and the remodeling and refurbishment of existing internal spaces. Works were also conducted by our Frameworks division.

The project, which lasted 46 weeks, included a new three storey extension and internal fit-out works, including new offices, communal, social and retail spaces, a coffee bar, and the addition of a lantern roof light.

The site was registered as part of our on-going commitment to the Considerate Constructor’s Scheme. The site team participated in a ‘Community Litter Pick’ as a gesture of goodwill to the community, and construction toys replicating the plant and materials used on site were also handed out to children in the local nursery.

McLauglin & Harvey are delighted to have worked on this important project, and would like to thank the staff and students of Stevenson College North Campus for their continued patience during the construction period.